ID
|
Task
Name
|
Done/Timing
|
|
1
|
Inception Phase
|
|
|
2
|
Setting up of Project Secretariat
Team
|
þ
February – June 2003
|
|
3
|
Nomination of National Focal Points
and National Coordinators
|
þ
March – April 2003
|
|
4
|
Establishment of Project Steering
Committee (PSC)
|
þ
March – April 2003
|
|
5
|
Drafting of Project Implementation
Plan (IP)
|
þ
March – May 2003
|
|
6
|
Establishment of Expert Group
|
þ
April – May 2003
|
|
7
|
First Expert Group Meeting
|
þ
July 2003
|
|
8
|
Revision of Project IP
|
þ
July – August 2003
|
|
9
|
Sub-regional Inception
Workshop/PSC Meeting I
|
þ
August 2003
|
|
10
|
Recruitment of 1st International
Consultant
|
þ
June – August 2003
|
|
11
|
Recruitment of 2nd International
Consultant
|
þ
August – October 2003
|
|
12
|
Recruitment of 3rd International
Consultant
|
þ
October – Dec. 2003
|
|
13
|
Final
Revision & Endorsement of IP
|
þ
Sep.
– December 2003
|
|
14
|
Recruitment
of Domestic Consultants
|
þ
Sep.
2003 – Mar. 2004
|
|
15
|
Implementation Phase
|
|
|
16
|
Activity I Prototype
Development
|
|
|
17
|
Preparation of Technical Papers on
Core Environmental Concerns & Indicators and Guidelines
on Environmental Performance Assessment (EPA)
|
þ
October – November 2003
|
|
18
|
Second Expert Group Meeting
|
þ
November 2003
|
|
19
|
Preparation of Guideline for Policy
and Institutional Analysis
|
þ
March 2004
|
|
20
|
Database Design (Fact Sheet)
|
þ
April 2004
|
|
21
|
Technical Workshop
|
þ
May 2004
|
|
22
|
Activity II Country-specific Activities
|
|
|
23
|
Setting up National Project Management
Office (NPMO)
|
þ
June 2004
|
|
24
|
Establishment of National Coordination
Committee (NCC)
|
þ
July – September 2004
|
|
25
|
Prioritization of environmental concerns,
reviewing policy targets, and selection of related indicators
using P-S-R model
|
þ
July – August 2004
|
|
26
|
Drafting of policy & institutional
analysis report
|
þ
July – August 2004
|
|
27
|
National Workshop I &
NCC Meeting I
|
þ
August – Sep. 2004
|
|
28
|
Final selection and reviewing of
environmental concerns and policy targets, and preparation
of indicator fact sheets
|
þ
October – December 2004
|
|
29
|
Preparation of policy & institutional
analysis report
|
þ
October – December 2004
|
|
30
|
Preparation for national workshop
II & technical training & EPA exercise
|
þ
November – December 2004
|
|
31
|
Setting up a review team for EPA
exercise & selection of municipalities/provinces
for the case studies
|
þ
December 2004 – January 2005
|
|
32
|
National Workshop II
& NCC Meeting II
|
þ
December 2004 – January 2005
|
|
33
|
Technical training &
EPA exercise
|
þ
December 2004 – January 2005
|
|
34
|
Preparation of EPA report by EPA
team
|
January – February 2005
|
|
35
|
Working on case studies
|
January – April 2005
|
|
ID
|
Task
Name
|
Timing
|
|
36
|
Subregional Workshop II/PSC
Meeting II
|
14 March 2005
|
|
37
|
WGE Meeting
|
15-16 March 2005
|
|
38
|
Preparation of national workshop
III
|
April 2005
|
|
39
|
National Workshop III
& NCC Meeting III
|
May 2005
|
|
40
|
Finalization of EPA reports and case
studies reports
|
June 2005
|
|
41
|
Activity III Subregional-specific
Activities
|
|
|
42
|
Selection of subregional environmental
concerns & reviewing of subregional policy targets
& objectives
|
April 2005
|
|
43
|
Selection of related indicators &
development of indicator fact sheets
|
May 2005
|
|
44
|
Drafting of subregional policy and
institutional analysis reports
|
June 2005
|
|
45
|
Database Design & Development
|
April - June 2005
|
|
46
|
Setting up of subregional review
team for EPA exercise & selection of areas for case
studies
|
June 2005
|
|
47
|
Third Expert Group Meeting
|
July 2005
|
|
48
|
EPA Exercise
|
July 2005
|
|
49
|
Working on case studies
|
August 2005
|
|
50
|
Development of Decision Support
System
|
April – July 2005
|
|
51
|
Finalization of Subregional EPA
Report
|
August 2005
|
|
52
|
Dissemination Phase
|
|
|
53
|
Website Development and Updating
& GMS E-net Development
|
June 2004-December 2005
|
|
54
|
Documents/Media Production and Dissemination
|
July – December 2005
|
| |
Preparation for PSC Meeting III
|
August 2005
|
|
55
|
Subregional Workshop
III & PSC Meeting III
|
September 2005
|
|
56
|
Regional Workshop
|
October 2005
|
|
57
|
End of Project
|
December 2005
|